Duplainville Road and Trail

Detour Route (09/26/2022)

The contractor will be placing asphalt near the intersection of Duplainville Road and Green Road on 09/27.  This progress will require tmeporary closures of the intersection throughout the day as the asphalt is placed.  Be prepared to utilize an alternate route for access along Duplainville Road.

While Duplainville Road is closed to thru traffic, residents and businesses with direct access along Duplainville Road will have that access maintained.  There is concrete paving from the The CP Rail System railroad tracks south of Green Road to the Capitol Drive overpass.  During paving and subsequent concrete curing days, there will be a hard closure along this portion of the road. This part of Duplainville Road will be closed to thru traffic.  Everyone should follow the contractor's directions to maintain safe and steady traffic flow.

The bridge over Spring Creek will be closed starting on 09/06 for reconstruction.  Please see the Duplainville Road Bridge Replacement webpage for more details and contact information.

Work will be occurring at the CP Rail System railroad tracks south of Green Road until the end of the month.  During this time, all traffic between the tracks and Green Road should enter and exit from the north.  Additionally, the east leg of the Duplainville Road and Green Road intersection will be closed for reconstruction from 09/19 to the end of the month.  During this time, all traffic that needs to use this intersection should enter and exit from the west side of Duplainville Road.

Subdivisions should be accessed through Lindsay Road.  Additional traffic control devices at the intersection of Redford Boulevard and Lindsay Road have been installed.  Subdivision access points along Duplainville Road will remain blocked off until fall of this year.

Duplainville Detour Routes - Final

Construction Update (09/22/2022)

The contractor is finishing the installation of underground utilities along the northern section of the project corridor.  Grading crews continue to prepare the roadway base between the Capitol Drive overpass and Weyer Road for paving.  Fiber optic line relocations and hydrant adjustments continue.  Asphalt driveway paving will start the week of 09/26.  Concrete paving will continue to be installed between the CP Rail System railroad tracks and Capitol Drive.  There are hard closures during periods of concrete paving and curing.

**Note: One task the contractor must complete for concrete paving is sawcutting the road.  This will typically be done at night following the placement of pavement.

Construction Update (09/15/2022)

The contractor is continuing to install underground utilities along the northern section of the project corridor.  Grading crews are preparing the roadway base between the Capitol Drive overpass and Weyer Road, as well as between the CP Rail System railroad tracks and Green Road.  Concrete pavement continues to be installed south of the Capitol Drive overpass once these preparations are complete.  There are hard closures during periods of concrete paving and curing.

**Note: One task the contractor must complete for concrete paving is sawcutting the road.  This will typically be done at night following the placement of pavement.



June 13, 2022

The contractor has started pulverizing Duplainville Road, clearing trees, and installing erosion control products.  The current plan is to install and replace existing underground utilities starting this week.

The consultant has set up an optional email communication to keep you up-to-date on where the contractor is working and where potential delay may exist.  If you are interested in enrolling in this email communication list, please send an email to Ashley Pridemore at Ashley.Pridemore@strand.com.  If you do not have email, please contact Ashley Pridemore at (414) 271-0771, or call our office at (262) 691-0804 to discuss alternative options or if you have further construction questions.

All thru traffic along Duplainville Road from the railroad crossing to Weyer Road should follow the posted detour along Redford Boulevard/County Highway F.

All businesses and residents along Green Road between Duplainville Road and Springdale Road/County Highway SR should enter and exit from the intersection of Green Road and Highway SR.

All businesses and residents along Green Road between Duplainville Road and Highway F should enter and exit from the intersection of Green Road and Highway F.


December 10, 2021

The City is replacing Duplainville Road from the Canadian National railroad tracks to Weyer Road. The new road will be concrete pavement where the road abuts businesses with heavier traffic, and asphalt pavement where the road abuts residential neighborhoods. This project includes adjustments to the road to account for developments in the area made since the road was previously rehabilitated. These adjustments include converting the two-way stop at the intersection of Duplainville Road and Green Road to a four-way stop, installing new storm structures to improve drainage in the area and adding a multi-use asphalt trail. The trail will be parallel to Duplainville Road for the length of the road reconstruction. The trail will also connect the Pewaukee Sports Complex to Duplainville Road at the intersection of Duplainville Road and Lindsay Road. The City of Pewaukee is working with Waukesha County to make sure the trail will continue through the new intersection of Lindsay Road and Redford Boulevard.

Construction plans are nearing completion. The City of Pewaukee and consulting engineers have scheduled a public involvement meeting on Monday, January 10, 2022, at 4:00 PM in the City’s Council Chambers. Construction will take place in 2022.